Task | Description | Cost | |||
---|---|---|---|---|---|
Property Annual Taxes (3 years estimated) | Three Years of property Tax |
$60000.00 | |||
Estimated Building Construction Costs | This includes the construction, furnishing, fixturing, |
$5450000.00 | |||
Estimated Landscape Construction Costs | This includes all landscape proposed from grass, |
$84520.00 | |||
Estimated Parkade and Site Construction Costs | This includes within property fire hydrant, power, water, |
$2108700.00 | |||
Estimated Fees Costs for Site Services from Local Authorities | This includes estimated fees of servicing the lot with fire hydrant, |
$212136.00 | |||
Building Permit Municipal Fees | This includes environmental micro-biology lab testing, new parkade development, |
$99615.00 | |||
Building Permit and Construction Plans and Documentation: | This includes the cost of Professional services from architect(s) and Engineers |
$287500.00 | |||
Development Permit Fees | This includes the design and consultation fees as well as the municipal |
$60488.00 | |||
Land Cost (remaining amount) | Thanks to our community we were able to pay $500,000, |
$400000 | |||
Subtotal $8762959 | |||||
Total Cost: $8762959 |